Copenhagen Infrastructure Partners to sell 50% stake in Scottish BESS project to AXA IM Alts
Copenhagen Infrastructure Partners (CIP), through its fund Copenhagen Infrastructure IV (CI IV), has signed an agreement to divest a 50% ownership stake in the Coalburn 1 battery energy storage system to AXA IM Alts, conditional on site commissioning.
Coalburn 1 is a 500MW, two-hour duration lithium-ion battery energy storage system located in South Lanarkshire, Scotland. CIP took a final investment decision in December 2023 and will continue to lead the project through construction and commissioning, expected in early 2026. Once operational, Coalburn 1 is expected to be the largest operational battery energy storage system in Europe.
The project has secured contracted revenues through a ten-year optimisation agreement with SSE and a fifteen-year capacity market agreement.
Coalburn 1 is one of three transmission-connected battery storage projects under construction by CIP in Scotland. Together, these projects will provide 1.5GW of power and 3GWh of electricity storage, sufficient to supply more than 4.5mn households for two hours. CIP is also developing an additional 4.5GW of battery storage projects across Scotland and England.
CIP’s CI V flagship fund recently exceeded a fund size of EUR 12bn, investing in renewable technologies including wind, solar PV and energy storage across Europe, North America and Asia Pacific.
CIP was advised by Ashurst (legal) and RBC Capital Markets (financial) on the Coalburn 1 transaction.