Ever since the Iberian power outage in the Spring of last year, and the subsequent discussions which pointed the finger at renewables, public interest in the grid continues to grow – well that’s if the number of articles being written about it as an indicator of public interest. Nonetheless, it’s safe to say that the grid as a topic is no longer confined to energy forecasts. In fact as we were reviewing DNV’s tenth energy transition outlook, The Times published Grid engineers fear they won’t be able to keep the UK’s lights on, which meant our starting point of the 163 page report would be the grid but focusing on why the grid has been so slow to expand. DNV’s answer goes beyond the usual suspect: permitting.
For all the attention it receives, permitting is only the first of the grid’s problems. In America, frustration has settled on regional operators and connection queues that have become a byword for delay. This is not in dispute. DNV’s argument is that clearing the paperwork faster solves less than it seems because of the obstacles faced further down the line – what it refers to as ‘a second layer of constraints.’ This comprises limited manufacturing capacity, long equipment lead times, shortages of specialized workers and fragmented procurement. Each region has its own bottleneck but our attention will be on Europe and North America in relation to China.
How long key equipment takes to arrive, according to industry. Every square is a month of waiting.
The data, which DNV draws from the IEA, sets out the waiting list in months, demonstrating the constraints that impede expansion. A transmission cable takes 24 to 36 months to arrive, while a large power transformer takes up to 48. DNV notes this is not a mass-produced part. In fact, transformers are frequently designed for specific voltages and networks. A direct-current cable, often preferred for long-distance lines, takes more than 60, with no upper limit given, and depends on a small group of qualified manufacturers. To cap it all, the final block shows why the list is slow to shorten: the IEA estimates that a new cable factory takes 36 to 48 months to build. According to DNV, capital alone will not fix this, as new factories also need trained workers, qualification processes and a credible long-term order book.
The contrast is sharpest in manufacturing. China has deep domestic capacity and long experience of building high-voltage networks. Europe and North America have no such cushion as both are contending with ageing assets, running several network programmes at once, equipment that takes years to arrive and a shortage of specialist workers. However, despite its domestic capacity, China is not immune. The sheer scale of its build-out, DNV points out, keeps its materials and factories under continuing pressure.
Annual spending on grids, USD bn. The coloured band marks each region's main growth phase; its lamp lights while that phase is under way.
Waiting is not the only price of a stretched supply chain; the equipment itself has become far more expensive. DNV, citing the IEA, reports that since 2019 cable prices have nearly doubled in real terms and transformer prices have risen by around 75%. The bill for building the grid will grow as well, though not everywhere at once. DNV expects the largest spending in China and North America, where electrification is adding the most capacity, with Europe next in line. China’s annual grid spending rises 61% between 2026 and 2045, from USD 258bn to USD 416bn. North America follows, with spending up 73% between 2030 and 2045 – from USD 212bn to USD 368bn, before growth slows. Europe is last. Its spending grows moderately until the mid-2030s, then rises 69% to 2050 from USD 186bn to USD 316bn.
Then there is labour. The shortage, DNV stresses, is not of construction workers or electricians in general but of specialists such as power-system planners, line and tower crews, protection and control engineers, relay technicians, high-voltage cable jointers and substation commissioning staff, along with the workers who build and test large transformers. Many of these roles demand several years of technical training and experience on live power systems.
The numbers are stark. Around 8 million people build, operate and maintain the world’s grids, and the report estimates that at least 1.5 million more will be needed by 2030, an increase of almost a fifth. In Europe the strain is already being felt. In a 2025 industry consultation cited by DNV, 96% of participants said shortages of skilled workers were slowing progress towards energy-transition targets.
None of this means permitting doesn’t hold sway. DNV itself calls it a major obstacle, and notes that in Europe and North America permitting and supply-chain delays continue to slow project delivery. Faster approvals would help, but the point is that they would not be enough. A project that clears its permits sooner still needs a factory slot, a cable crew and an engineer to commission it, and in Europe and North America all three are in short supply.
According to DNV, the remedy is steady, coordinated effort. Governments and grid operators will need to align their project pipelines, standardise equipment where they can, commit to buying it over longer periods, train more specialists and build regional supply chains. Without that, faster permitting may simply move projects through the first gate more quickly, only for them to wait at the next.